As a forward-looking, dynamic organisation, Addleshaw Goddard wanted to relocate its London-based operations from two separate London based locations to a contemporary new office building in central London. The prestigious Milton Gate building contains 200,000 sq ft of office space over seven floors, six of which are being occupied by Addleshaw Goddard. The Relocation provided Addleshaw Goddard with the opportunity to employ cutting-edge technology to create a flexible and innovative working environment for its employees. To achieve this, consideration of Addleshaw Goddard’s IT at the early RIBA stages of the project was central to the success of the Relocation. Having had previous experience of delivering other high-profile IT Relocation projects, PTS was employed as IT Consultancy Partner for Addleshaw Goddard’s project and to work alongside the other members of the professional team including the Construction Project Management company, Gardiner and Theobald Management Services (GTMS) and the Architect, MCM.

Highlights


  • IT Relocation Strategy for 500 people from two locations to new 200,000 sq ft premises
  • Flexibility, innovation, and quality built into IT infrastructure design and programme of works
  • Best practice print strategy to reduce carbon footprint and allow the introduction of intelligent printing
  • Forward-looking network design aligned with Addleshaw Goddard’s network improvement programme to enable a ‘thin’ data environment and improve energy efficiency
  • Integration with existing voice and desktop technology in other locations outside of Lonon
  • IT implementation and project management working alongside the professional team to ensure IT objectives were embedded and realised as part of the overall design programme

“In bringing together our London-based operations into new state-of-the-art business premises, Addleshaw Goddard has not only achieved greater operational efficiencies, but we have also been able to embrace the very latest technology and printing techniques to provide a creative and forward-looking environment. With PTS’s involvement as our IT Consultancy partner from the very earliest RIBA stages, we have been able to ensure that our business vision and IT needs were translated into tangible project objectives with attention to detail and quality throughout. With PTS’s support, we were able to bring our London Relocation project to a successful conclusion.” – Peter Thompson, Senior Project Manager for Addleshaw Goddard

Addleshaw Goddard Case Study

Summary


PTS was on hand throughout the duration of the project lifecycle to ensure that the execution of the IT Strategy was integrated seamlessly into Addleshaw Goddard’s overall Relocation programme

Relevant projects

Charles Russell Speechly

With Project Management and Relocation assistance, Charles Russell advances within the Middle East to a new premier location in the Bahrain World Trade Centre.

Read more

Rathbone Brothers

PTS assists Rathbone Brothers with the successful relocation of its London headquarters.

Read more

Clifford Chance

A Global Legal Firm develops global change management process with help from PTS

Read more
Book a Consultation